Analysis of cycle times and economic equipment matching in open pits based on optimum transportation costs using the MCDM method
Taşkın Deniz Yıldız 1✉ Email
Furkan Kerem Kasa 2 Email
1 Department of Mining Engineering Adana Alparslan Türkeş Science and Technology University Adana Turkey
2 Department of Mining Engineering Cukurova University Adana Turkey
Taşkın Deniz Yıldız 1 , Furkan Kerem Kasa2
1 Corresponding author, Adana Alparslan Türkeş Science and Technology University, Department of Mining Engineering, Adana/Turkey, tdyildiz@atu.edu.tr
2 Cukurova University, Department of Mining Engineering, Adana/Turkey, furkankasa@gmail.com
Abstract
In open-pit operations, the loading and handling process constitutes 30–50% of the total operating cost. Therefore, studies on the cycle times and compatibility of loaders and trucks enable the reduction of mining costs. In large-capacity operations, there may not only be a single loading point but also multiple unloading points. Therefore, planning based on optimum cycle times using multiple different loader-truck combinations in the presence of these loading and unloading points can reduce unit haulage costs and improve schedule efficiency, which may shorten the project duration and enhance operating profit. Accordingly, the aim is to optimize the minimum loader-truck operation cost and select the loader-truck with the lowest investment cost using a MCDM Method in a simple and efficient manner. First, the equipment-matching alternatives and evaluation criteria are defined. Criteria weights are then derived, and each alternative is scored and ranked using an MCDM approach. The highest value is then selected as the decision. These matches were compared with previous data, i.e., whether they had high investment costs, the number of machines and equipment, the amount of work they could do daily, and their unit costs. According to the results, a 10% improvement in cycle times results in a 2.6-year reduction in mine life. This corresponds to ~ 10% of the total overburden removal. Therefore, using programs that minimize cycle times can provide investors with significant reductions in transportation costs.
Keywords:
CAPEX
equipment selection
Haulage and transportation optimization
load and haul
OPEX
Multi Criteria Decision Making
A
1. Introduction
Raw material production through mining projects is a highly challenging process today due to the rapid advancements in industrial and technological fields. Mining companies should, on the one hand, strive to make their operations profitable based on existing technologies, and on the other hand, meet the material demands of industries. The transportation system in any mining operation is one of the most important elements, especially from a technical and economic perspective. The transportation system should transfer the planned ore/waste volume without disrupting the entire flow of the mining process and should be able to meet the technical challenges and costs introduced to the project. The selection process of a transportation system that considers all these factors is one of the challenging issues in any mining project. Although the truck-loader system is known as the preferred traditional transportation method in open-pits due to its low capital cost and high flexibility, it still creates high operating costs, safety issues, and environmental footprints (Abbaspour, 2020). At this point, there is a need to optimize loading and transportation for lower operating costs, ensuring safety, and a lower environmental footprint. Loading and transportation optimization includes factors such as cycle time, equipment efficiency, and the matching of loaders and trucks. Methods for minimizing cycle time, increasing overall equipment efficiency (such as comparing tonnage and volume efficiency), and achieving optimal loader-truck matching are being discussed worldwide. Equipment matching is essential for both size matching and number or fleet matching to shorten cycle time and minimize equipment time waste (You, 2025). Many large mining operations utilize dispatch systems, which track and analyze loader-truck data in real-time at the mines, resulting in more efficient operations.
In open-pits, numerous heavy pieces of equipment are used to increase productivity. Due to the large investments involved, no mining company can afford to invest in inefficient equipment utilization, as poor loader–truck matching increases equipment downtime. Therefore, careful attention should be paid to correctly matching equipment during the equipment selection process (Hoang et al., 2014). Choosing the right loader for an open-pit mine depends on the production quantities generated in short- and long-term planning, the type of mineral to be extracted, and the characteristics of the environment. Other factors should be considered when selecting equipment, especially how efficiently the loaders will operate with the selected truck fleets. Loading and transportation machines are selected according to the fill characteristics and geometry of the loaders or buckets. Since loader selection determines the performance of the trucks, both loaders and buckets should be selected before the trucks. Fleet and individual equipment sizes and capacities are generally limited by work area constraints. At this point, equipment matching is a crucial step in the overall decision-making process to determine the necessary mobile fleet (Karpuz and Hindistan, 2008; Erdem and Duran, 2017; Kahraman and Ağdere, 2022).
The current economy forces mining companies to maximize their profits over the mine’s life. Especially in the context of open pits, producing at minimum cost is essential. One of the major problems in the profitability of open pits is the inability to provide an efficient trucking system that can achieve significant cost reductions. The ability to reduce operating costs can be directly achieved through the efficient use of trucks and excavators (Kesimal and Başçetin, 2000; Chaowasakoo, 2017; Zeng et al., 2022). ~50–60% of the total mining cost is spent on the loading and transportation system. Therefore, determining transportation costs is critical to the economic feasibility of mining projects. Even a small saving in operating costs is considered a success (Subtil et al., 2011; Demir et al., 2012; Bellamkondi and Prakaash, 2020; Kaul and Soofastaei, 2022).
The time required for a truck to complete a cycle is defined as the cumulative sum of queuing time, loading time, unloading time, and travel time from one place to another (Mukundan and Narayan, 2025). The optimum number of trucks for an operation can be found by dividing the loader's unit capacity by the truck's capacity per unit time. The average loading time of a truck is directly related to the excavator's bucket filling factor and cycle time (Tosun, 2021). At this point, optimizing equipment selection and reducing waiting times can significantly reduce costs. In this regard, the selection and evaluation of mining equipment used in open-pit mines are based on investment and overall operating cost estimates. Before rationally arranging mining, equipment and systems consisting of loading machines, transport trucks, and crushing plants, a comprehensive analysis of technical and economic aspects such as investment and operating costs, which largely determine the costs of mining operations, should be carried out. In addition, the operational parameters of the mining equipment should also be considered (Patyk et al., 2021). The selection of truck types with different specifications is a crucial factor in ensuring the continuity of material transportation, considering the resulting costs. Transportation investment cost is the purchase price of trucks in an early mining project, based on the number of trucks needed for each route. Transportation costs consist of fixed costs such as operator wages and insurance, and variable costs such as fuel and consumables for trucks and excavators. Optimization models are being developed to determine truck allocation in open pits with the aim of minimizing the total cost consisting of transportation investment and operating costs (Isnafitri et al., 2021).
2. Differences of the Study from the Literature, and Scope & Methodology
2.1. Review of the Literature on the Subject of Study
Due to the current economic climate, significant increases in the cost items most used by mine investors, such as fuel, electricity, explosives, and transportation, are greatly raising production costs and putting economic strain on companies (Emiroğlu, 2019). According to a report by PricewaterhouseCoopers (PwC), reducing surface mining costs and increasing production volume alone are not sufficient for making the operation more efficient. According to the information provided, even if companies increase production volumes and reduce costs, they may still complain about low productivity values. The report concludes that productivity in mines depends on many factors, the most important of which are choosing the right equipment under the right production and economic conditions (Mining Turkey Magazine, 2014). At this point, in open-pits – before transitioning to full automation – the optimum number of trucks and loaders required for overburden removal and production should be determined during the investment period. Because calculating the optimum number of trucks-loaders will reduce the cycle time and consumable costs such as fuel, machinery/equipment, and materials in the investment and operation periods of open-pits. In this way, open-pits will avoid significant additional investment costs that could arise later due to an incorrect loader-truck count assessment.
The technical aspect of the selection process is likely the primary determinant of the numerous feasible loading and transportation system alternatives. Considering the differences between capital cost, operating cost, and the estimated lifetime of the equipment, a cost comparison may be necessary to evaluate the total cost per unit of production. Beyond traditional engineering economics analyses, another additional step is computer simulation of the various systems under consideration. Simulation selection ensures the correct choice of alternatives and also helps identify potential changes in system design that could result in the best alternatives (Başçetin, 2007). The inclusion of Industry 4.0 in the processes of all mining companies and the use of simulations and other digital technologies can save mining companies from losses and production shortages. Making predictions for the future will help increase profitability in mines, improve safety, and optimize their operations and processes (Karikari and Askari-Nasab, 2023). According to the analysis by Dzakpata et al. (2016) on the most efficient loader-truck matching orientation for cost optimization, 45% of the loader's working time is spent identifying trucks. This demonstrates the inherent losses in truck-loader dispatch and management in mines. Improvements in the truck dispatch system can achieve much higher available time and usage time for the truck fleet. (Erçelebi and Kırmanlı, 2000) examined the surface mining equipment selection techniques found in the literature. They classified these techniques as classical, optimization research, and artificial intelligence techniques. Among the optimization research techniques, the most commonly used methods are linear and integer programming, simulation, and queuing theory. Artificial intelligence methods have become quite popular in recent years, and expert systems, knowledge-based decision systems, and genetic algorithm techniques have been frequently applied in mining equipment selection. According to (Faraji, 2013) and (Chaowasakoo, 2017), the main shortcomings in the models examined in the literature are: a) insufficient consideration of the waiting time and queues of excavators and loaders, b) simplification of the models and the consideration of a limited amount of detail in the models, c) neglecting the stochastic nature of the truck and excavator transportation system, and d) development of a model based on a homogeneous fleet (trucks and excavators). The developed software overcomes the difficulties in selecting appropriate equipment, which is crucial for surface mining operations, and provides significant savings (Kesimal and Başçetin, 2000; Erçelebi and Başçetin, 2009; Kırmanlı and Erçelebi, 2009).
With these developments, multi-criteria decision-making (MCDM) methods have become useful for a wide variety of applications in the mining sector for ~ 20 years. Their role in the decision-making process, where multiple conflicting criteria are considered under both precise and uncertain conditions, is of great importance (Sitorus et al., 2016). Today, due to the very high capital cost of surface mining equipment, any error in the selection of quantity, type, and capacity of equipment can have an irreparable impact on the net present value of the mining project. Equipment selection is a complex, MCDM problem. For example, (Bazzazi et al., 2011), proposed a new MCDM method that considers both tangible and intangible factors in the mining equipment selection problem, enabling the selection of the most suitable equipment that satisfies the decision-maker. The results showed a significant reduction in computational time consumption and good accuracy compared to traditional methods such as the fuzzy Analytical Hierarchy Process (AHP) method. (Rakhmangulov et al., 2024) ranked the four groups of criteria (technical, technological, environmental, economic, and organizational) according to their importance using the MCDM method when considering the complex truck selection criteria. (Alpay and Iphar, 2018) selected the most suitable hydraulic excavator for a magnesite mine using fuzzy TOPSIS (Technique for Order Preference by Similarity to an Ideal Solution) and VIKOR (Multi-Criteria Compromise Ranking), which are fuzzy MCDM methods.
36% of publications on this topic deal solely with the problem of mining method selection. The remaining publications relate to areas such as ore enrichment, mining geology, post-mining activities, and health, safety, and environment (Sitorus et al., 2016). Furthermore, while numerous publications exist in the literature on optimizing loader-truck cycle times and increasing operational efficiency, there is a noticeable lack of studies optimizing loader-truck selection with the aim of reducing investment and operating costs and increasing efficiency using the MCDM method. Considering this deficiency, this study aims to optimize loader-truck cycle times and select the most efficient loader-truck with minimum cost to achieve this.
2.2. Scope and Methodology
This study aimed to demonstrate the critical role of truck-loader dispatch in transporting overburden material from 5 different loading points in the mine to 6 different dumping sites (Fig. 1) throughout the mine's lifecycle. In particular, the truck's carrying capacity, one of the most important parameters affected by cycle time, was considered a key parameter in this study. The methodological steps are summarized in Fig. 2:
Fig. 1
Truck-excavator match (Representative image).
Click here to Correct
Fig. 2
Summary of the study's workflow.
Click here to Correct
1.
Overburden removal operations carried out throughout the mine's lifetime are considered data entry.
2.
Based on this data, the required number of trucks and excavators (needs) has been determined.
3.
25 different matches were made using 5 different truck models and 5 different excavator models (from low capacity to high capacity).
4.
The working capacity of the loading points from the open pit and the capacity of the dumping areas have been determined as constraints.
5.
Distances from loading points to these dumping sites were determined, and truck cycle times were calculated for each loading area-dumping site match based on these distances.
6.
The optimal quantity of material to be hauled and dumped at each dump site was determined through optimization
7.
The minimum transportation operating cost derived from this, and defined as the objective function, was taken for each truck-excavator match.
8.
Investment costs for trucks and excavators have been calculated for each match.
9.
The optimal dispatch was found, and the result was compared with the result obtained from the MCDM method.
10.
The findings were discussed in conjunction with the literature review, and the conclusions, the theoretical and practical contributions of the study, the limitations of the study, and suggestions for future research were presented.
Figure 1. Truck-excavator match (Representative image).
Figure 2. Summary of the study's workflow.
Although calculations and analysis of machinery and equipment investments and other data could reveal suitable options, this is currently a rather laborious and primitive approach. Human errors and mistakes can occur during analyzes. Therefore, the Weighted Sum Model was applied in the MCDM analysis in this study. In this method, decision options were determined. The options used in the model were: low unit truck cost (non-beneficial), high daily transport capacity of the truck (beneficial), low number of trucks and excavators (non-beneficial), and low investment amount (non-beneficial). Then, the weight of each decision option was determined, a decision table was created in the study, and the value of each match was summed as a score, and the highest value - that is, the closest to 1 - was selected as the decision. From this, the best decision matches were identified. These matches were compared with previous data, i.e., whether they have high investment costs, the number of machines and equipment, the amount of work they can do daily, and their unit costs.
3. Equipment Selection and Analysis for the Overburden Process
3.1. Calculation of the Number of Truckloads Required
CAT brand mining equipment, specifically 770 series trucks and hydraulic excavators of models 365, 374, 385, 6015, and 6018, were used in the match process. These 25 truck-excavator matches are presented in Table 1. The capacities (transport and load) of each machine, fuel consumption per km and per hour, and excavator cycle time were taken from catalog values. The data obtained in this study are presented in Table 2. In this table, the data is as follows: 1) The columns for "Total number of trucks required" and "Total number of loaders required" are calculated values. 2) The columns for loader bucket capacity, loader cycle time, truck capacity, fuel consumption by the truck, and fuel consumption by the loader represent data taken from the machines' catalogs.
Table 1
Truck-excavator matches.
 
Excavator
 
Match
365C L
374D/F
385C
6015/6015 FS
6018/6018 FS
Truck
770G
A1
A2
A3
A4
A5
772G
B1
B2
B3
B4
B5
773G
C1
C2
C3
C4
C5
775G
D1
D2
D3
D4
D5
777G
E1
E2
E3
E4
E5
Table 2
Data obtained from calculations (indicated by H) and catalog data (indicated by K).
Total number of trucks required (H)
Total number of loaders required
(H)
Loader bucket capacity (m3) (K)
Loader cycle time (sec) (H)
Truck capacity (tons) (K)
Truck fuel (lt/km) (K)
Fuel loader (lt/h) (K)
Match (H)
16
4
5.3
36
38
3.44
43
A1
16
4
5.4
38
38
3.44
46
A2
16
5
5.4
42
38
3.44
52
A3
15
2
8.1
28
38
3.44
106
A4
15
2
10.6
44
38
3.44
168
A5
13
4
5.3
36
46.8
3.89
43
B1
13
4
5.4
38
46.8
3.89
46
B2
14
5
5.4
42
46.8
3.89
52
B3
12
2
8.1
28
46.8
3.89
106
B4
13
3
10.6
44
46.8
3.89
168
B5
11
4
5.3
36
61
5.11
43
C1
11
4
5.4
38
61
5.11
46
C2
11
5
5.4
42
61
5.11
52
C3
10
2
8.1
28
61
5.11
106
C
10
3
10.6
44
61
5.11
168
C5
10
4
5.3
36
70.5
5.56
43
D1
10
4
5.4
38
70.5
5.56
46
D2
10
5
5.4
42
70.5
5.56
52
D3
9
2
8.1
28
70.5
5.56
106
D4
9
3
10.6
44
70.5
5.56
168
D5
7
4
5.3
36
105
8.00
43
E1
7
4
5.4
38
105
8.00
46
E2
7
5
5.4
42
105
8.00
52
E3
6
2
8.1
28
105
8.00
106
E4
6
3
10.6
44
105
8.00
168
E5
Table 1. Truck-excavator matches.
Table 2. Data obtained from calculations (indicated by H) and catalog data (indicated by K).
3.2. Truck Cycle Time and Haulage Capacity
Cycle times and truck transport capacities, central to this study, are among the most important parameters to be examined to operate an efficient transportation system. In mining operations, it is critical planning that excavators do not remain idle or transport trucks do not have to wait in line to take loads from excavators. Therefore, careful evaluation of machine cycle times and synchronized truck movements without waiting is necessary. As mentioned above, there are 5 different areas (Areas A, B, C, D, and E) and 6 different dumping sites in the mining area. The distances between these areas and dumping sites are presented in Table 3.
Table 3
The distances between loading areas and dumping sites, and the calculated cycle times to these points.
 
Dumping areas (km)
 
DS-1
DS-2
DS-3
DS-4
DS-5
DS-6
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Production Areas (km)
Area-A
2.5
738.2
1.8
603.8
3.2
872.6
4.1
1,045.4
5.5
1,314.2
6.2
1,448.6
Area-B
3.8
987.8
2.1
661.4
1.5
546.2
2.9
815.0
4.3
1,083.8
5.8
1,371.8
Area-C
6.1
1,429.4
4.5
1,122.2
2.8
795.8
1.6
565.4
2.2
680.6
3.9
1,007.0
Area-D
7.8
1,755.8
6.2
1,448.6
4.9
1,199.0
3.1
853.4
1.4
527.0
2.5
738.2
Area-E
9.1
2,005.4
7.8
1,755.8
6.5
1,506.2
4.8
1,179.8
2.9
815.0
1.2
488.6
3.2.1. Truck Cycle Time
The cycle time of trucks is the total time taken during one transport trip. This time includes the truck's travel time, return time, docking ime, and unloading time. The cycle time of each truck is calculated considering the following parameters: a) Loaded speed (km/h), b) Unloaded speed (km/h), c) Loading time (min), d) Unloading time (min), e) Capacity (m³). Accordingly, the maximum speed of the trucks within the site will be fixed at 25 km/h when loaded and 30 km/h when unloaded. The capacity is the catalog value, and the loading time is the loading time calculated by the excavator. In this case, the cycle time calculation is performed separately for each match using the following formula, creating Table 3. Here, ds: Distance from loading area to dumping area, Vloaded: Speed ​​while loaded, Vunloaded: Speed ​​while unloaded, tloading: Time it takes for the excavator to load the truck, tunloading: Time it takes for the truck to unload, 3600: Conversion factor to seconds.
Table 3. The distances between loading areas and dumping sites, and the calculated cycle times to these points.
3.2.2. The Effect of Cycle Duration
If a 10% reduction in cycle time can be achieved, this indicates that the truck will complete the loading and unloading process 10% faster. This shows that it performs a greater amount of work per unit of time, and consequently, the unit cost decreases. For example, in the E4 configuration, the truck capacity is 105 tons, the excavator bucket volume is 8.1 m3, and the cycle time is 28 seconds. When these values are substituted into the calculation of the required number of trucks and excavators, the cycle time is calculated as 1716 seconds. In contrast, the daily workload of one truck is 4211 m3/day.
Assuming a 10% reduction in cycle time, the truck cycle time will be 1544 seconds and the truck workload will be 4679 m3/day. In this case, 4679–4211 = 468 m3/day of material will be transported in excess compared to the previous situation. Considering 330 working days per year and a project life of 25 years, 468 m3/day x 330 days x 25 = 3,861,000 m3 of extra work can be done. Multiplying this amount by the required truck calculation (6 trucks), the total equals 6 x 3,861,000 m3 ≌ 23 million m3. Since the total amount of overburden removal to be done throughout the project life is 218,000,000 m3, 218/25 = 8.7 million m3 of overburden removal will be performed annually throughout the project life. In this case, it means the project lifespan could be shortened by 23 million m3 / 8.7 million m3 = 2.6 years. This also represents ~ 10% of the project. This shows that significant cost savings can be achieved by shortening the cycle time. Since a shorter mine life means no more environmental permits, licensing permits, and other fixed costs, it will further increase the project's economic viability.
3.3. Overburden Costs and Machinery-Equipment Investment
In surface mining preparatory work, overburden removal operations constitute a significant portion of the costs (Özdemir, 2023b). The relationship between the unit truck overburden removal cost and transport capacity is shown in Fig. 3. This demonstrates the relationship between increasing the amount of work done per unit time and decreasing the unit cost. The purchase prices of the trucks and excavators used in this study are presented in Table 4 in USD ($). Based on this data, the investment cost and the unit operating costs of the truck-excavator for each match, according to the previously determined number of machines, were calculated and presented in Table 5. The truck unit cost shown in Table 5 is the operating cost and includes only diesel fuel consumption. Other costs are included in the overburden removal cost. In the calculation of the overburden removal cost; The total work volume (218,000,000 m³), ​​including all items such as explosives, materials, labor, machinery maintenance and repair, general production and management costs, was divided by the overburden volume, and the unit overburden costs (given in the last column) were calculated. Examining the unit costs of the trucks, even with different matches, the unit costs are essentially the same. The important point here is that these unit costs were not derived from transportation based on distances to the dumping sites, but rather from a fixed average daily round-trip distance. When optimization was performed by considering cycle times that included the distance to each dumping site, it was observed that these costs decreased by ~ 25%. This result can contribute to a more realistic economic evaluation of the project.
Fig. 3
The relationship between unit cost and truck capacity.
Click here to Correct
Table 4
The purchase costs of the machines.
Model
Purchase costs ($)
770G
1,000,000
772G
1,100,000
773G
1,200,000
775G
1,300,000
777G
1,500,000
365C L
400,000
374D/F
720,000
385C
850,000
6015/6015 FS
700,000
6018/6018 FS
2,000,000
Table 5
Unit costs.
Match
Overburden cost (TL)
Truck unit cost ($/m3)
Excavator unit cost ($/m3)
Overburden cost ($/m3)
A1
14,072,225,997
0.61
1.32
1.61
A2
14,093,275,872
0.61
1.41
1.62
A3
14,135,375,622
0.61
1.59
1.62
A4
14,505,583,984
0.57
3.25
1.66
A5
14,940,614,734
0.57
5.15
1.71
B1
14,060,934,845
0.56
1.32
1.61
B2
14,081,984,720
0.56
1.41
1.61
B3
14,133,910,552
0.60
1.59
1.62
B4
14,493,156,138
0.52
3.25
1.66
B5
14,938,012,970
0.56
5.15
1.71
C1
14,075,181,400
0.62
1.32
1.61
C2
14,096,231,275
0.62
1.41
1.62
C3
14,138,331,025
0.62
1.59
1.62
C4
14,504,320,992
0.56
3.25
1.66
C5
14,939,351,742
0.56
5.15
1.71
D1
14,073,640,549
0.61
1.32
1.61
D2
14,094,690,424
0.61
1.41
1.62
D3
14,136,790,174
0.61
1.59
1.62
D4
14,501,643,447
0.55
3.25
1.66
D5
14,936,674,197
0.55
5.15
1.71
E1
14,074,650,943
0.62
1.32
1.61
E2
14,095,700,818
0.62
1.41
1.62
E3
14,137,800,568
0.62
1.59
1.62
E4
14,496,490,438
0.53
3.25
1.66
E5
14,931,521,188
0.53
5.15
1.71
Figure 3. The relationship between unit cost and truck capacity.
Table 4. The purchase costs of the machines.
Table 5. Unit costs.
3.4. Optimization
The following data were used in the optimization: distances from loading areas to unloading areas (Table 3), cycle times of the trucks depending on these distances (Table 3), and cycle time calculation parameters for each truck (Loaded speed (km/h), unloaded speed (km/h), loading time (min), unloading time (min), capacity (m³)). The objective function is as follows:
Click here to Correct
Click here to Correct
Click here to Correct
Here, Xij is the amount of load transported in m³, and Cij is the unit cost. The constraints are as follows:
1. The maximum total production constraint hat can be achieved from the loading areas:
2. The maximum total storage capacity constraint that can be achieved at the dumping site:
3. Total project overburden capacity constraint:
The model setup was solved using MS Excel Solver. The model's results before and after the solution is presented in Fig. 4. As can be seen, all constraints are met. The unit cost of each machine resulting from this optimization is presented in Table 6. Table 6 shows the change in unit cost (color change) from the lowest cost (green) to the highest cost (red). (All values must be multiplied by 1,000,000. The table has been simplified for presentation.)
Fig. 4
Setup before optimization and after optimization results.
Click here to Correct
Table 6
Overburden unit costs of matches ($/m3).
Matches
365C L
374D/F
385C
6015
6018
770G
0.1399
0.1349
0.1459
0.1434
0.1605
772G
0.1409
0.1360
0.1474
0.1451
0.1629
773G
0.1440
0.1395
0.1520
0.1501
0.1701
775G
0.1258
0.1190
0.1250
0.1207
0.1346
777G
0.1288
0.1223
0.1294
0.1255
0.1346
Figure 4. Setup before optimization and after optimization results.
Table 6. Overburden unit costs of matches ($/m3).
3.5. Finding the Best Match and MCDM Analysis
A
Although the calculations made so far could reveal a suitable option by examining the tables, this is currently a rather laborious and primitive method. Errors and mistakes stemming from human factors may occur during interpretation. Therefore, the Weighted Sum Model was applied in this study for MCDM analysis. In this method, decision options were determined. The options to be used in the model are as follows: a) Unit truck cost: Should be low (i.e., non-beneficial), b) Daily transport capacity of the truck: Should be high (i.e., beneficial), c) Number of trucks and excavators: Should be low (i.e., non-beneficial), d) Investment amount: Should be low (i.e., non-beneficial). In this method, those whose outcome we want to minimize are calculated as "non-beneficial" (minimum value / value), and those whose outcome we want to maximize are calculated as "beneficial" (value / maximum value). The data should first be normalized using linear normalization. In this case, non-beneficial and beneficial options should be transformed using the following formula: Non-beneficial = (Minimum value / value), and beneficial = (value / maximum value). Then, the weight of each decision option should be determined. The sum of the weights cannot exceed 1. In our model, these weights were chosen as follows: a) Unit truck cost: 0.35, b) Daily transport capacity of the truck: 0.30, c) Number of trucks and excavators: 0.1 each, d) Investment amount: 0.15. These values ​​are multiplied by each converted value and written in the Table 7.
Table 7
Raw data and decision scores.
Loader truck matches
Unit transportation cost
Truck daily transport capacity
Number of trucks
Number of excavators
Investment
Final scores
Raw data ($/m3)
Decision scores
Raw data (ton)
Decision scores
Raw data
Decision scores
Raw data
Decision scores
Raw data ($)
Decision scores
A1
0.14
0.30
1811
0.11
16
0.04
4
0.05
17,600,000
0.07
0.57
A2
0.13
0.31
1804
0.11
16
0.04
4
0.05
20,480,000
0.06
0.57
A3
0.15
0.29
1784
0.11
16
0.04
5
0.04
23,450,000
0.06
0.53
A4
0.14
0.29
1911
0.12
15
0.04
2
0.10
22,900,000
0.06
0.61
A5
0.16
0.26
1890
0.12
15
0.04
2
0.10
26,500,000
0.05
0.57
B1
0.14
0.30
2177
0.14
13
0.05
4
0.05
14,600,000
0.09
0.62
B2
0.14
0.31
2167
0.14
13
0.05
4
0.05
17,180,000
0.08
0.61
B3
0.15
0.28
2137
0.13
14
0.04
5
0.04
21,050,000
0.06
0.56
B4
0.15
0.29
2323
0.15
12
0.05
2
0.10
19,000,000
0.07
0.65
B5
0.16
0.26
2291
0.14
13
0.05
3
0.07
25,500,000
0.05
0.56
C1
0.14
0.29
2731
0.17
11
0.05
4
0.05
12,600,000
0.10
0.67
C2
0.14
0.30
2716
0.17
11
0.05
4
0.05
14,980,000
0.09
0.66
C3
0.15
0.27
2669
0.17
11
0.05
5
0.04
17,450,000
0.07
0.61
C4
0.15
0.28
2965
0.19
10
0.06
2
0.10
16,400,000
0.08
0.70
C5
0.17
0.24
2913
0.18
10
0.06
3
0.07
21,000,000
0.06
0.62
D1
0.13
0.33
3080
0.19
10
0.06
4
0.05
11,600,000
0.11
0.74
D2
0.12
0.35
3060
0.19
10
0.06
4
0.05
13,880,000
0.09
0.74
D3
0.13
0.33
3001
0.19
10
0.06
5
0.04
16,250,000
0.08
0.70
D4
0.12
0.34
3380
0.21
9
0.07
2
0.10
15,100,000
0.09
0.81
D5
0.13
0.31
3313
0.21
9
0.07
3
0.07
19,500,000
0.07
0.72
E1
0.13
0.32
4213
0.26
7
0.09
4
0.05
8,600,000
0.15
0.87
E2
0.12
0.34
4176
0.26
7
0.09
4
0.05
10,580,000
0.12
0.86
E3
0.13
0.32
4067
0.25
7
0.09
5
0.04
12,650,000
0.10
0.80
E4
0.13
0.33
4797
0.30
6
0.10
2
0.10
11,200,000
0.12
0.95
E5
0.13
0.31
4662
0.29
6
0.10
3
0.07
15,000,000
0.09
0.85
Here, Kd is the calculated decision value, Wj is the determined weight value (between 0 and 1), and Xij is the transported load. Then, the decision table (Table 7) was obtained in the study. Here, the value of each match is summed as a score on the right side, and the highest value, closest to 1, is selected as the decision. Examining the Table 7, we see that the best decision is the E4 match with 0.95, and the second-best option is E1. Comparing these with the previous data in a table, we obtain the data in Table 8. As can be seen, although the E4 match has a higher investment cost compared to E1, it has fewer machines and equipment, can do more work daily, and has a lower unit cost.
Table 8
Comparing the two highest scores.
Comparing/match
E4 (777G-6015)
E1 (777G-365C L)
Investment (Million $)
11.2
8.6
Number of trucks
6
7
Number of excavators
2
4
Daily transport capacity (tons)
4797
4212
Unit cost ($/ton)
0.1255
0.1288
Table 7. Raw data and decision scores.
Table 8. Comparing the two highest scores.
4. Discussion
In surface mining, transportation equipment constitutes a significant portion of total operating costs. Therefore, optimizing fleet performance and truck-loaders is crucial for reducing costs and increasing productivity. In these truck-loader systems, loading equipment plays a vital role, as truck efficiency depends on loader performance. The matching factor, a metric that evaluates the compatibility between loaders and trucks, is commonly used to improve fleet efficiency. However, many current approaches fail to account for practical mining conditions such as equipment downtime, road conditions, climatic effects, optimum truck cycle times, and material fragmentation from blasting (Bodziony et al., 2018; Mohtasham, 2025). At this point, optimization studies are a widely accepted method for evaluating complex systems. In some cases, it may not be possible to make the desired changes in the actual system and monitor the resulting effects. Optimization studies come into play precisely at this point, allowing the researcher to make possible changes and receive feedback at the lowest possible cost (Saadatmand-Hashemi and Sattarvand, 2015).
In the literature (Choi et al., 2009; Kun et al., 2013; Patyk et al., 2021; Patyk and Bodziony, 2022; Özdemir, 2023a), analyses have been conducted using the MCDM method to increase mining efficiency in open-pits, achieve the most cost-effective truck-loader matching, process optimization, and optimal transportation routes. Analyses have also been conducted using discrete event simulation (Zeng et al., 2022; Karikari and Askari-Nasab, 2023; Mirzaei-Nasirabad et al., 2023; Mohtasham and Mirzaei-Nasirabad, 2023), sometimes including cycle times in the analysis, with the aim of improving similar parameters. In addition, mixed integer linear programming methods (Pourrahimian and Askari-Nasab, 2009; Torkamani and Askari-Nasab, 2011; Burt et al., 2018) have also been used in improving these parameters. Studies (Olaleye and Adagbonyin, 2011; Adams and Bansah, 2016; Akınola and Ahmed, 2022) have been conducted to identify and reduce operational delays. (Choi and Nieto, 2011; Vahdatikhaki and Hammad, 2014; Chaowasakoo et al., 2014; 2017; Pamungkas and Mulyono, 2023) have performed different analyses using GPS and other tracking systems to determine cycle time and improve mining efficiency by reducing this time. Improvements to the route and other technical specifications of operations can also increase cycle time and operational efficiency, and reduce costs (Aksoy, 2005; Aksoy et al., 2005; Patyk and Bodziony, 2018; Krysa et al., 2021). (Bellamkondi and Prakaash, 2020; Matsimbe, 2020; Elijah et al., 2021) used queuing theory to reduce cycle time. (Krause and Musingwini, 2007; Erdem and Korkmaz, 2012; Özdoğan and Özdoğan, 2017; Dey et al., 2017; Nakousi et al., 2018; Cheng, 2019; Bakhtavar and Mahmoudi, 2020; Ghaziania et al., 2021; Aguayo et al., 2022; Mnzool et al., 2024) have conducted analyses aimed at reducing cycle time, thereby lowering costs and increasing efficiency. (Kırmanlı, 2004; Kırmanlı and Erçelebi, 2005) used excavator and truck purchase costs to identify the lowest-cost combination for each excavator and truck that provides the desired production. The studies mentioned above yielded results parallel to the findings in this article. The main basis of all these studies in the literature is to reduce cycle time in mining operations. This is because the term "cycle time," which is affected by many parameters, can contribute to a wide range of areas in mining, from increasing production and reducing costs to the economic operation and evaluation of resources and equipment, and the most efficient and shortest possible depletion of mineral resources.
Similar to the findings in our article, (Nday and Thomas, 2019) found that a reduction in cycle time resulted in higher tonnage per hour and per shift, thus increasing mine production and lowering operational costs. By optimizing productivity through systems thinking, output can be increased with the same resources and fixed costs. As a result, the increase in the mine's financial performance can extend its lifespan by providing access to previously uneconomical resources. This positive impact on the country will be tangible through royalties, taxes, and the economy. In our article, while assuming the mine's assets are fixed, shortening the operating life ensures earlier cash flow and faster integration of the mines into the economy without incurring fixed costs over time. The relationship between the unit truck overburden cost and transport capacity—that is, the relationship between the increased amount of work done per unit time and the decreased unit cost—is shown in Fig. 3. The important thing is not choosing a large-capacity truck-excavator, but selecting machinery and equipment suitable for the mine's operating capacity and ensuring their harmonious operation. Of course, it is possible to choose larger machines. However, in this case, problems negatively affecting cycle times may arise due to mismatches in either the excavator or the truck. As these machines get larger, their maneuverability may decrease significantly compared to smaller equipment. Therefore, these selected machines and equipment will not be used efficiently.
Similar to the findings in this article, the literature (Başçetin, 2007; Burt et al., 2011; da Cunha Rodovalho et al., 2016; Ribeiro Lages et al., 2020) also emphasizes that the selection of large equipment does not guarantee efficiency and minimum cost in mining operations under all circumstances, and that there are optimum points in this selection.
5. Conclusion and Suggestions
This article presents results obtained by considering average cycle times and average truck speeds. While varying according to mine capacity, a 10% improvement in cycle times resulted in a 2.6-year reduction in mine life in this study. This corresponds to ~ 10% of the total overburden removal. This leads to a decrease in fixed costs and operational costs, as more work can be done per unit of time. Delays in cycle times, however, affect mine life and bring about additional costs. Therefore, using programs that minimize cycle times can significantly reduce not only performance but also transportation costs for investors.
This study demonstrates that the MCDM method can be effectively applied in mining operations during the investment and post-investment periods, considering operational capacities and cycle times, to facilitate rapid decision-making. Furthermore, this article reveals that selecting large-capacity trucks and excavators does not necessarily lead to reduced operating costs or increased operational efficiency. The key is not choosing large-capacity trucks and excavators, but selecting machinery and equipment suitable for the mine's operating capacity and ensuring their harmonious operation. Of course, it is possible to choose larger machines. However, in this case, problems negatively affecting cycle times may arise due to mismatches in either the excavator or the truck. As these machines grow larger, their maneuverability may decrease significantly compared to smaller equipment. Therefore, these selected machines and equipment will not be used efficiently.
5.1. Theoretical and Practical Contributions of the Study
This study analyzes the optimization of loader-truck combinations using the MCDM method to reduce cycle time and minimize operating costs. First, multiple loader and truck models were selected to create combinations. Then, the distances between loading and unloading areas were included in the calculation to determine the minimum investment and unit operating cost, and the minimum cycle time. The loader-truck combination that best supports the company's economic operation was then selected. Determining the optimum number of loader-truck allows for the optimal calculation of investment (such as purchase and depreciation costs) and operating costs (such as fuel, oil, tires, vehicle parts replacements, and maintenance costs) of the selected loaders and carriers during the investment period. This, along with other cost items, allows for the calculation of the ratio of loading and transportation costs to investment and operating costs in open-pits.
This article focuses on the relationship between cycle time and cost in loader-truck selection, providing a support tool for mining operators to make optimal decisions during or after the investment phase. Unlike previous literature, this article applies the Weighted Sum Model with MCDM and identifies the most cost-effective loader-truck selection as a decision-maker's choice. This ensures that potentially overlooked data remains mathematically present in the system, creating a support mechanism for rapid decision-making. This mechanism will allow mining operators to obtain alternative solutions by comparing parameters or modifying their weightings to find the most advantageous match. The results of this article are expected to improve cost estimation and increase equipment efficiency in mining operations by focusing on the lowest investment and operating costs in the equipment selection process. By using the MCDM method, mining operators can make quick decisions regarding the most suitable equipment match by evaluating multiple criteria simultaneously within the same operating process using a simple scoring method.
5.2. Limitations of the Study
Although the method in this study is applied only to the overburden removal process, it can also be applied in studies that consider the effect of ore grade, a parameter not included in the overburden removal process. Furthermore, while this article does not examine all parameters and efficiencies in surface mining, as mentioned above, it is possible to examine mining processes as a whole by increasing the number of these parameters. The study matches trucks and excavators involved in transporting overburden material from 5 different loading points to 6 different dumping sites. However, this match does not consider equipment performance, breakdown/maintenance losses, the impact of climatic conditions, the effects of routes and paths, and the size of the material after blasting on the loader and truck, etc. Additionally, this article assumes that all truck and loader equipment was purchased as unused equipment at the beginning of the investment phase. In other words, a match was made without considering both fleet aging and the simultaneous shipment of truck and loader equipment of different ages to different routes.
This study analyzes the investment costs of loaders-trucks, the unit cost of overburden, and the unit costs per m3 of trucks and loaders used for overburden. Furthermore, while direct materials (such as diesel fuel), consumables, and machinery and equipment materials that affect the unit cost have been included in the calculations, costs such as depreciation and labor, which can be considered as fixed values, have not been considered.
5.3. Future Research
In this study, an analysis was conducted by considering the age of the loader and truck equipment as fixed. On the other hand, using this model, all kinds of quantitative data that will affect the selection of loader-truck equipment can be determined as criteria. At this point, it is recommended that new studies be conducted to develop a score-based MCDM method by including more criteria in the evaluation.
As this study shows, it is possible to solve such problems without using complex algorithms and methods. Just as it is impossible to predict the results of uncertainties arising from human-based studies with 100% accuracy, it is also impossible to achieve 100% satisfactory results in sectors like mining where dozens of parameters need to work synchronously and harmoniously. However, with the super-fast development of artificial intelligence technology, it will be possible to achieve optimal results by reducing decision-making processes to very short timeframes and taking advantage of the space opened up for intervention. Therefore, considering the time value of money, it is recommended to prioritize such studies.
In the future, to ensure more efficient and synchronized operation, it will be beneficial to use alert programs that can monitor cycle times in real-time and ensure that cycle times remain within certain limits. In addition, dispatch systems that can optimally manage and control artificial intelligence technologies or machines within the open-pits may also be considered. Programs that can integrate these systems will contribute to decision-making mechanisms that create predictable scenarios.
Annex 1. Equipment Selection for the Overburden Process
1. Calculating the Number of Loader Required
H = 10 + 0.57 (Cc − 6) (Jimeno et al., 1995). In this formula, Cc: The bucket size of the loader (m3) (bucket capacity), H: Bench height, so if a bench height of 12 meters is chosen, Cc = 9.51 m3 is calculated. Thus, a bucket capacity of up to 9.51 m3 can be determined. If the loader has a bucket capacity of 8.1 m3 for an average excavation density of 2.30 t/m3, and a cycle time of 25 seconds, the hourly capacity of the loader can be calculated according to the following formula: Vlc = [a x Kf x Rw ] / [(1 + k) x T]. In this formula, the symbols and their meanings are as follows: Vlc: Loader's hourly capacity, a: Selected bucket volume (8.1 m3), Moh: Amount of overburden excavation to be made per hour (m3/h), Kf: Bucket filling factor (0.90), Rw: Workplace efficiency (85%), k: Swelling factor (0.3), T: Bucket cycle time (25 sec). Vlc = [8.1 m3 x 0.90 x 0.85] / [(1 + 0.3) x 25 sec] = 0.190 m3/sec = 686.38 tons/h. Moh/Vlc = [0.4330 / 0.275] m3/sec = 2.10. Therefore, an average of 2 active loaders are required for the stripping of the entire site. Since there are 25 different matches in this study, not all calculations are shown here; only an example calculation is presented.
2. Loader Net Uptime & Productivity Analysis
The meanings and units of the terms to be used in the calculations are as follows:
• Possible hours (Typ): The company's scheduled annual operating time (hours/year),
• Unused hours (by+a): Faults and annual periodic maintenance (hours/year),
• Net mechanical time available for use (Tm) = Available hours (Tp) – Unused hours (Typ)
• Mechanical availability (Ktt) = [Possible hours (Tp) – Unused hours (Typ)] / Possible hours (Tp)
• Actual net working time (Tn) (Time losses due to weather conditions, compatibility factors, etc., Tk) = Tm – Tk
• With mechanical efficiency = (Tn / Tm), the loader used for excavation will be active for an average of 2.10/3 = 70% of its net operating time (excluding downtime and breakdowns) throughout its entire service life. Therefore, considering its backups, the required net operating time is approximately Tn = 70% x 24 (h/day) x 300 (days/year) = 5028.54 hours/year.
3. Calculation of Required Number of Trucks
3.1. Selection of a truck compatible with the loader
Here, a CAT 775G (56-ton) loader has been selected. The loader will fill the truck at an average speed of 0.19 m³/s (= 0.19 m³/sec x 2.30 tons/m³ (tons/sec) x 25 seconds = 10.96 tons/cycle) with a bucket cycle time of 25 seconds. Considering different truck types, the loader selection is as follows: If the 56-ton 775G truck is selected, [56 tons / (10.96 tons / loader cycle time)] = 5.11. This means that with an average of 5 passes (5 x 10.96 tons = 54.80 tons), 97.88% of the truck's capacity can be loaded. Therefore, this truck was chosen. Calculating the required number of loaders also requires calculating the truck's cycle time.
• T: Truck cycle time = tm + tb + tg + td
• tm (Maneuver time) + tb (Uploaded time) = (20) + (34.50) = 54.5 sec,
• tg: Time spent on the road during a loaded trip,
• td: Time spent on the road during an empty return trip,
5 pass x 25 sec (Loader bucket cycle time) = 125 sec. T= (54.5 + 125 + 289 + 199.71) sec = 668.21 sec. This value (668.215 sec) is the maximum cycle time for a truck in the mine site.
3.2. The truck's minimum hourly capacity
[56 tons x 90% (efficiency)] / 668.21 sec = 0.075 tons/sec = 271.53 tons/h = > 686.58 (tons/h) / 271.53 (tons/h) = 2.53. So, the capacity of one loader is equivalent to ~ 3 trucks.
3.3. The average number of active trucks required for overburden removal at the mine site
The average number of active trucks required for overburden removal at the mine site = (Average hourly capacity of a loader / Average hourly capacity of a truck) => (686.58 tons/h) / (271.53 tons/h) = 2.45 (trucks/loader). This means that for 3 actively working loaders (2.45 trucks/loader), 3 loaders equal 7.36 trucks, or 8 trucks in terms of capacity for overburden.
A
Funding
No budget was used for this article.
A
Data Availability
• The datasets used and/or analysed during the current study available from the corresponding author on reasonable request.
Authorship Contribution Statement
Taşkın Deniz Yıldız: Writing – review & editing, Methodology, Writing – original draft, Conceptualization. Furkan Kerem Kasa: Writing – review & editing, Methodology, Writing – original draft, Data curation, Software.
A
Author Contribution
Taşkın Deniz Yıldız: Writing – review & editing, Methodology, Writing – original draft, Conceptualization. Furkan Kerem Kasa: Writing – review & editing, Methodology, Writing – original draft, Data curation, Software.
References
Abbaspour, H. Transportation system selection in open-pit mines (Truck-Shovel and IPCC systems) based on the technical, economic, environmental, safety, and social (TEcESaS) indexes. (2020).
Adams, K. K. & Bansah, K. J. Review of Operational Delays in Shovel-Truck System of Surface Mining Operations, 4th UMaT Biennial International Mining and Mineral Conference, pp. MP 60–65. (2016).
Aguayo, I. A. O., Nehring, M. & Ullah, G. M. W. Simulating the productivity improvements of incorporating a surge loader into the open pit loading and haulage system. Int. J. Min. Reclam. Environ. 36 (6), 381–398. https://doi.org/10.1080/17480930.2022.2047528 (2022).
Akınola, A. P. & Ahmed, Y. M. Determination of Load-Haul Equipment Match Factor at Ashaka Cement Quarry, Gombe State, Nigeria. ABUAD J. Eng. Res. Dev. 5 (2), 28–34 (2022).
Aksoy, C. O. Minimizing the Economic Unit Cost of Dragline Truck Shovel Operation at Yatagan Eskihisar Open Pit Mine Turkey. CIM Bull. 98, 1088, 1–4 (2005).
Aksoy, C. O. et al. Truck-shovel optimization accounting for cost, safety, and operational practice. CIM Bull. 98, 1090 (2005).
Bakhtavar, E. & Mahmoudi, H. Development of a scenario-based robust model for the optimal truck-shovel allocation in open-pit mining. Comput. Oper. Res. 115, 104539. https://doi.org/10.1016/j.cor.2018.08.003 (2020).
Başçetin, A. Karar destek sistemleri ve maden mühendisliği uygulamaları (Decision support systems and mining engineering applications). TMMOB Chamber of Mining Engineers Publication no. 139, ISBN: 978-9944-89-412-8, Ankara, Available via: < (2007). http://www.maden.org.tr/yayinlar/kitap_goster.php?kodu=88
Bellamkondi, S. & Prakaash, M. P. Optimization of shovel-dumper combination in an open cast mine using simulation software. Int. J. Res. Appl. Sci. Eng. Technol. 8 (9), 1250–1259 (2020).
Bodziony, P., Patyk, M. & Kasztelewicz, Z. Analysis of operating states of haul trucks used in surface mining. Journal of KONES, 25. (2018). https://doi.org/10.5604/01.3001.0012.2776
Burt, C., Caccetta, L., Welgama, P. & Fouché, L. Equipment selection with heterogeneous fleets for multiple-period schedules. J. Oper. Res. Soc. 62 (8), 1498–1509. https://doi.org/10.1057/jors.2010.107 (2011).
Burt, C. N., Caccetta, L. & Chan, Y. Utilisation-based equipment selection. In: (eds Burt, C. & Caccetta, L.) Equipment Selection for Mining: With Case Studies. Studies in Systems, Decision and Control, vol 150. Springer, Cham. https://doi.org/10.1007/978-3-319-76255-5_8 (2018).
Chaowasakoo, P., Leelasukseree, C. & Wongsurawat, W. Introducing GPS in fleet management of a mine: Impact on hauling cycle time and hauling capacity. Int. J. Technol. Intell. Planning. 10 (1), 49–66. https://doi.org/10.1504/IJTIP.2014.066711 (2014).
Chaowasakoo, P. Matching truck-and-shovel operations in open-pit mines using statistical data-dispatching strategies, match factor, and age-based maintenance. (2017).
Chaowasakoo, P., Seppälä, H., Koivo, H. & Zhou, Q. Digitalization of mine operations: Scenarios to benefit in real-time truck dispatching. Int. J. Min. Sci. Technol. 27 (2), 229–236. https://doi.org/10.1016/j.ijmst.2017.01.007 (2017).
Cheng, J. E. Match factor determination of excavator-truck combination in surface mining: Case study of merit pila coalfield, Sarawak. Geol. Behav. 3 (1), 28–29. http://doi.org/10.26480/gbr.01.2019.28.29 (2019).
Choi, Y., Park, H. D., Sunwoo, C. & Clarke, K. C. Multi-criteria evaluation and least‐cost path analysis for optimal haulage routing of dump trucks in large scale open‐pit mines. Int. J. Geogr. Inf. Sci. 23 (12), 1541–1567 (2009).
Choi, Y. & Nieto, A. Optimal haulage routing of off-road dump trucks in construction and mining sites using Google Earth and a modified least-cost path algorithm. Autom. Constr. 20 (7), 982–997. https://doi.org/10.1016/j.autcon.2011.03.015 (2011).
da Rodovalho, C., Lima, E., de Tomi, G. & H. M., & New approach for reduction of diesel consumption by comparing different mining haulage configurations. J. Environ. Manage. 172, 177–185. https://doi.org/10.1016/j.jenvman.2016.02.048 (2016).
Dey, S., Mandal, S. K. & Bhar, C. Analysis of factors, which influence the cycle time of dumpers of open cast coal mines to improve production. Modelling Meas. Control C. 78 (3), 289–302 (2017).
Demir, E., Karpuz, C. & Demirel, N. Design and implementation of a multimodel transportation cost analysis model for domestic lignite Supply in Turkey. South. Afr. Inst. Min. Metall. 112, 993–998 (2012). Available via: < https://www.saimm.co.za/Journal/v112n11p993.pdf%3E
Dzakpata, I., Knights, P., Kizil, M. S., Nehring, M. & Aminossadati, S. M. Truck and shovel versus in-pit conveyor systems: a comparison of the valuable operating time. 2016 Coal Operators' Conference, Wollongong, Australia, 10–12 Feb 2016. Wollongong, Australia: The University of Wollongong Printery. (2016).
Elijah, K. et al. Optimisation of shovel-truck haulage system in an open pit using queuing approach. Arab. J. Geosci. 14, 973. https://doi.org/10.1007/s12517-021-07365-z (2021).
.Emiroğlu, A. Magazine preface. TMD Sector News Bulletin, 76, 6–7. Available via: < (2019). https://www.tmder.org.tr/depolama/2024/12/FILE_F98805-84B12C-8C34BD-D5642C-7B5A83-68627D.pdf&gt
Erçelebi, S. G. & Kırmanlı, C. Review of surface mining equipment selection techniques. Chapter in Mine Planning and Equipment Selection 2000, ISBN: 9780203747124, Routledge, 1st Edition. (2000).
Erçelebi, S. G. & Başçetin, A. Optimization of shovel-truck system for surface mining. J. South Afr. Inst. Min. Metall. 109, 433–439 (2009).
Erdem, B. & Duran, Z. Temel Madencilik Bilgileri (Mining Basics). Chapter 4 in Açık İşletmelerde Makine Ekipman Seçimi (Machinery Equipment Selection in Open Pit Mines). ISBN: 978-605-64724-1-1, Ankara, pp.247–417. Available via: < (2017). https://madencilikturkiye.com/wp-content/uploads/2019/04/Temel-Madencilik-Bilgileri-www.madencilikturkiye.com_.pdf
Erdem, B. & Korkmaz, F. Analysis of dragline cycle time components. J. Min. Sci. 48 (3), 545–558. https://doi.org/10.1134/S1062739148030185 (2012).
Faraji, R. A comparison between linear programming and simulation models for a dispacthing system in open pit mines. École Polytechnique de Montréal, PhD thesis. (2013).
Ghaziania, H. H., Monjezi, M., Mousavi, A., Dehghani, H. & Bakhtavar, E. Design of loading and transportation fleet in open-pit mines using simulation approach and metaheuristic algorithms. J. Min. Environ. 12 (4), 1177–1188 (2021).
A
Hardy, R. J. Selection criteria for loading and hauling equipment: Open pit mining applications. Curtin University of Technology, PhD thesis. (2007).
Hoang, N., Luat, D. T., Hoa, L. T. T., Hoan, D. N. & Van Viet, P. Determination of shovel-truck productivities in open-pit mines. In The 3rd International Conference on Advances in Mining and Tunneling, Vung Tau. Publishing House for Science and Technology (pp. 103–108). (2014).
Isnafitri, M. F., Rosyidi, C. N. & Aisyati, A. A truck allocation optimization model in open pit mining to minimize investment and transportation costs. In IOP Conference Series: Materials Science and Engineering (Vol. 1096, No. 1, p. 012024). IOP Publishing. (2021). https://doi.org/10.1088/1757-899X/1096/1/012024
Jimeno, C. L., Jimeno, E. L. & Carcedo, F. J. A. Drilling and Blasting of Rock. Geomining Technological Institute of Spain, First edition, Rotterdam, Netherlands, ISBN: 90-5410-199-7. (1995).
Karikari, Y. S. & Askari-Nasab, H. Oil Sand Operation Simulation Using HAULSIM-Practical Guide. Mining Optimization Laboratory, ISBN: 978-1-55195-503-2, pp.220–228. (2023).
Kahraman, H. A. & Ağdere, Y. Selecting appropriate equipment in mining operations. Min. Türkiye Magazine. 107, 54–55 (2022). Available via: < https://madencilikturkiye.com/wp-content/uploads/2018/09/Madencilik-Turkiye-Dergisi-Sayi-107-fgt54jhgk98.pdf%3E
A
Kahraman, M. M. & Dessureault, S. Continuous innovation. Min. Türkiye Magazine. 27, 116–117 (2012). Available via: < https://www.mtmagaza.com/wp-content/uploads/2018/05/Madencilik-Turkiye-Dergisi-Sayi-27-wedcv56.pdf%3E
Karpuz, C. & ve Hindistan, M. A. Açık işletmelerde üretim yöntemleri (Production methods in open pits). Chapter 3 in Maden Mühendisliği Açık Ocak İşletmeciliği El Kitabı (Mining Engineering Open Pit Mining Handbook), pp.115–207. (2008).
Kaul, A. & Soofastaei, A. Advanced analytics for mine materials transportation. Chapter in Advanced Analytics in Mining Engineering: Leverage Advanced Analytics in Mining Industry to Make Better Business Decisions (pp. 613–647). (2022). https://doi.org/10.1007/978-3-030-91589-6_19
Kesimal, A. & Başçetin, A. Replacement study of off-highway trucks in an open-pit coal mine in Turkey. Mineral. Resour. Eng. 9 (02), 279–286. https://doi.org/10.1142/S0950609800000226 (2000).
Kırmanlı, C. Açık işletmelerde optimum ekipman seçimi (Optimal equipment selection in open-pit mines). Istanbul Technical University, PhD thesis. (2004).
Kırmanlı, C. & Erçelebi, S. G. Optimal equipment selection in open-pit mines. I T U J. 4 (2), 67–78 (2005). Available via: < http://itudergi.itu.edu.tr/index.php/itudergisi_d/article/view/657%3E
A
Kırmanlı, C. & Erçelebi, S. G. An expert system for hydraulic excavator and truck selection in surface mining. J. South. Afr. Inst. Min. Metall. 109 (12), 727–738 (2009). Available via: < https://www.saimm.co.za/Journal/v109n12p727.pdf%3E
Krause, A. & Musingwini, C. Modelling open pit shovel-truck systems using the Machine Repair Model. J. South Afr. Inst. Min. Metall. 107 (8), 469–476 (2007).
Krysa, Z., Bodziony, P. & Patyk, M. Discrete Simulations in Analyzing the Effectiveness of Raw Materials Transportation during Extraction of Low-Quality Deposits. Energies 14, 5884. https://doi.org/10.3390/en14185884 (2021).
Kun, M., Topaloglu, S. & Malli, T. Evaluation of wheel loaders in open pit marble quarrying by using the AHP and Topsis Approaches / Ocena pracy ładowarki na podwoziu kołowym w odkrywkowej kopalni marmuru w oparciu o metody AHP i topsis. Arch. Min. Sci. 58 (1), 255–267. 10.2478/amsc-2013-0018 (2013).
A
Madencilik Türkiye & Dergisi PwC’ye Göre, Açık İşletmelerde Ekipmanların Uygun Kullanımı Üretimde Artış Sağlıyor. Madencilik Türkiye Dergisi, 41, 34. Erişim: (2014). https://www.mtmagaza.com/wp-content/uploads/2018/05/Madencilik-Turkiye-Dergisi-Sayi-41-45677sbrb.pdf
Matsimbe, J. Optimization of shovel-truck productivity in quarries. Int. J. Res. Advent. Technol. 8 (10), 1–9. 10.32622/ijrat.810202008 (2020).
Mirzaei-Nasirabad, H. et al. An optimization model for the real-time truck dispatching problem in open-pit mining operations. Optim. Eng. 24, 2449–2473. https://doi.org/10.1007/s11081-022-09780-x (2023).
Mohtasham, M. & Mirzaei-Nasirabad, H. Evaluating the performance of the DISPATCH algorithm, a commercial software, in the Sungun copper mine. J. Geomine. 1 (3), 117–122. https://doi.org/10.22077/jgm.2024.7379.1020 (2023).
Mohtasham, M. Development of a Match Factor for Optimizing Haulage Fleet Efficiency in Open-Pit Mining Operations. J. Min. Environ. https://doi.org/10.22044/jme.2025.16360.3188 (2025).
Mnzool, M. et al. Optimization of cycle time for loading and hauling trucks in open-pit mining. Min. Mineral. Deposits. 18 (1), 18–26. https://doi.org/10.33271/mining18.01.018 (2024).
Nakousi, C., Pascual, R., Anani, A., Kristjanpoller, F. & Lillo, P. An asset-management oriented methodology for mine haul-fleet usage scheduling. Reliab. Eng. Syst. Saf. 180, 336–344. https://doi.org/10.1016/j.ress.2018.07.034 (2018).
Nday, I. N. M. & Thomas, H. Optimization of the cycle time to increase productivity at Ruashi Mining. J. South Afr. Inst. Min. Metall. 119 (7), 631–638. https://doi.org/10.17159/2411-9717/624/2019 (2019).
Olaleye, B. M. & Adagbonyin, P. E. Simulation of loading and haulage of fragmented rock in a typical granite quarry in Ondo State, Nigeria. J. Emerg. Trends Eng. Appl. Sci. 2 (5), 884–890 (2011).
Özdoğan, M. & Özdoğan, H. Cycle time segments and cycle time distribution curves of mining size wheel loaders-a case study. Sci. Min. J. 56 (1), 13–21 (2017).
Özdemir, A. C. Use of integrated AHP-Topsis Method in selection of optimum mine planning for open-pit mines. Arch. Min. Sci. 68 (1), 35–53. https://doi.org/10.24425/ams.2023.144316 (2023a).
Özdemir, A. C. İstatistiksel yöntemlerin dekapaj miktarının belirlenmesinde kullanılabilirliği ve bir açık ocak krom sahasına uygulanması (Modelling of stripping amount by working time in open-pit mines). Cukurova Univ. J. Fac. Eng. 38 (1), 41–48. https://doi.org/10.21605/cukurovaumfd.1273692 (2023b).
Pamungkas, G. J. & Mulyono, N. B. Optimizing Coal Hauling Operations: A Strategic Plan for Increased Productivity at PT Borneo. Logistic Operation Manage. Res. 2 (1), 63–83. https://doi.org/10.31098/lomr.v2i1.1529 (2023).
Patyk, M. & Bodziony, P. Analysis of multiple criteria selection and application of APEKS method in haul truck mining transport process. In E3S Web of Conferences (Vol. 71, p. 00003). EDP Sciences. (2018). https://doi.org/10.1051/e3sconf/20187100003
Patyk, M. & Bodziony, P. Application of the analytical hierarchy process to select the most appropriate mining equipment for the exploitation of secondary deposits. Energies 15, 5979. https://doi.org/10.3390/en15165979 (2022).
Patyk, M., Bodziony, P. & Krysa, Z. A multiple criteria decision making method to weight the sustainability criteria of equipment selection for surface mining. Energies 14, 3066. https://doi.org/10.3390/en14113066 (2021).
Pourrahimian, Y. & Askari-Nasab, H. Optimizing block extraction sequence with MIP method and investigating the effect of road condition on truck cycle time. Mining Optimization Laboratory (MOL) Research Report One, University of Alberta, 168–188. (2009).
Ribeiro Lages, A. et al. Distribution of the main operational costs due to the size of the loading and haulage fleet: Brazilian reality. In: Topal, E. (eds) Proceedings of the 28th International Symposium on Mine Planning and Equipment Selection - MPES 2019. Springer Series in Geomechanics and Geoengineering. Springer, Cham. (2020). https://doi.org/10.1007/978-3-030-33954-8_38
Saadatmand-Hashemi, A. & Sattarvand, J. Simulation based investigation of different fleet management paradigms in open pit mines-a case study of sungun copper mine. Arch. Min. Sci. 60 (1), 195–208. https://doi.org/10.1515/amsc-2015-0013 (2015).
Subtil, R. F., Silva, D. M. & Alves, J. C. A practical approach to truck dispatch for open pit mines. In 35Th APCOM symposium, 24–30 September, Wollongong, NSW, 765–777. (2011).
Torkamani, E. & Askari-Nasab, H. A mathematical programming model for optimal truck-shovel allocation. MOL Research report three 2010/2011. Min. Optim. Lab. 106, 99–105 (2011).
Tosun, A. Determination of optimum truck number at open coal quarry. Arch. Min. Sci. 66 (2), 213–225. https://doi.org/10.24425/ams.2021.137458 (2021).
Vahdatikhaki, F. & Hammad, A. Framework for near real-time simulation of earthmoving projects using location tracking technologies. Autom. Constr. 42, 50–67. https://doi.org/10.1016/j.autcon.2014.02.018 (2014).
You, G. G. Production schedule optimization. Chapter in Mining Project Value Optimization pp. 147–164 (Springer, 2025). https://doi.org/10.1007/978-981-97-7883-6_7
Zeng, W., Baafi, E. Y. & Fan, H. A simulation model to study truck-allocation options. J. South Afr. Inst. Min. Metall. 122 (12), 741–750. https://doi.org/10.17159/2411-9717/2100/2022 (2022).
Click here to Correct
Click here to Correct
Click here to Correct
Click here to Correct
Table 1. Truck-excavator matches.
 
Excavator
 
Match
365C L
374D/F
385C
6015/6015 FS
6018/6018 FS
Truck
770G
A1
A2
A3
A4
A5
772G
B1
B2
B3
B4
B5
773G
C1
C2
C3
C4
C5
775G
D1
D2
D3
D4
D5
777G
E1
E2
E3
E4
E5
Table 2. Data obtained from calculations (indicated by H) and catalog data (indicated by K).
Total number of trucks required (H)
Total number of loaders required
(H)
Loader bucket capacity (m3) (K)
Loader cycle time (sec) (H)
Truck capacity (tons) (K)
Truck fuel (lt/km) (K)
Fuel loader (lt/h) (K)
Match (H)
16
4
5.3
36
38
3.44
43
A1
16
4
5.4
38
38
3.44
46
A2
16
5
5.4
42
38
3.44
52
A3
15
2
8.1
28
38
3.44
106
A4
15
2
10.6
44
38
3.44
168
A5
13
4
5.3
36
46.8
3.89
43
B1
13
4
5.4
38
46.8
3.89
46
B2
14
5
5.4
42
46.8
3.89
52
B3
12
2
8.1
28
46.8
3.89
106
B4
13
3
10.6
44
46.8
3.89
168
B5
11
4
5.3
36
61
5.11
43
C1
11
4
5.4
38
61
5.11
46
C2
11
5
5.4
42
61
5.11
52
C3
10
2
8.1
28
61
5.11
106
C
10
3
10.6
44
61
5.11
168
C5
10
4
5.3
36
70.5
5.56
43
D1
10
4
5.4
38
70.5
5.56
46
D2
10
5
5.4
42
70.5
5.56
52
D3
9
2
8.1
28
70.5
5.56
106
D4
9
3
10.6
44
70.5
5.56
168
D5
7
4
5.3
36
105
8.00
43
E1
7
4
5.4
38
105
8.00
46
E2
7
5
5.4
42
105
8.00
52
E3
6
2
8.1
28
105
8.00
106
E4
6
3
10.6
44
105
8.00
168
E5
Table 3. The distances between loading areas and dumping sites, and the calculated cycle times to these points.
 
Dumping areas (km)
 
DS-1
DS-2
DS-3
DS-4
DS-5
DS-6
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Distance (km)
Cycle time (sec)
Production Areas (km)
Area-A
2.5
738.2
1.8
603.8
3.2
872.6
4.1
1,045.4
5.5
1,314.2
6.2
1,448.6
Area-B
3.8
987.8
2.1
661.4
1.5
546.2
2.9
815.0
4.3
1,083.8
5.8
1,371.8
Area-C
6.1
1,429.4
4.5
1,122.2
2.8
795.8
1.6
565.4
2.2
680.6
3.9
1,007.0
Area-D
7.8
1,755.8
6.2
1,448.6
4.9
1,199.0
3.1
853.4
1.4
527.0
2.5
738.2
Area-E
9.1
2,005.4
7.8
1,755.8
6.5
1,506.2
4.8
1,179.8
2.9
815.0
1.2
488.6
Table 4. The purchase costs of the machines.
Model
Purchase costs ($)
770G
1,000,000
772G
1,100,000
773G
1,200,000
775G
1,300,000
777G
1,500,000
365C L
400,000
374D/F
720,000
385C
850,000
6015/6015 FS
700,000
6018/6018 FS
2,000,000
Table 5. Unit costs.
Match
Overburden cost (TL)
Truck unit cost ($/m3)
Excavator unit cost ($/m3)
Overburden cost ($/m3)
A1
14,072,225,997
0.61
1.32
1.61
A2
14,093,275,872
0.61
1.41
1.62
A3
14,135,375,622
0.61
1.59
1.62
A4
14,505,583,984
0.57
3.25
1.66
A5
14,940,614,734
0.57
5.15
1.71
B1
14,060,934,845
0.56
1.32
1.61
B2
14,081,984,720
0.56
1.41
1.61
B3
14,133,910,552
0.60
1.59
1.62
B4
14,493,156,138
0.52
3.25
1.66
B5
14,938,012,970
0.56
5.15
1.71
C1
14,075,181,400
0.62
1.32
1.61
C2
14,096,231,275
0.62
1.41
1.62
C3
14,138,331,025
0.62
1.59
1.62
C4
14,504,320,992
0.56
3.25
1.66
C5
14,939,351,742
0.56
5.15
1.71
D1
14,073,640,549
0.61
1.32
1.61
D2
14,094,690,424
0.61
1.41
1.62
D3
14,136,790,174
0.61
1.59
1.62
D4
14,501,643,447
0.55
3.25
1.66
D5
14,936,674,197
0.55
5.15
1.71
E1
14,074,650,943
0.62
1.32
1.61
E2
14,095,700,818
0.62
1.41
1.62
E3
14,137,800,568
0.62
1.59
1.62
E4
14,496,490,438
0.53
3.25
1.66
E5
14,931,521,188
0.53
5.15
1.71
Table 6. Overburden unit costs of matches ($/m3).
Matches
365C L
374D/F
385C
6015
6018
770G
0.1399
0.1349
0.1459
0.1434
0.1605
772G
0.1409
0.1360
0.1474
0.1451
0.1629
773G
0.1440
0.1395
0.1520
0.1501
0.1701
775G
0.1258
0.1190
0.1250
0.1207
0.1346
777G
0.1288
0.1223
0.1294
0.1255
0.1346
Table 7. Raw data and decision scores.
Loader truck matches
Unit transportation cost
Truck daily transport capacity
Number of trucks
Number of excavators
Investment
Final scores
Raw data ($/m3)
Decision scores
Raw data (ton)
Decision scores
Raw data
Decision scores
Raw data
Decision scores
Raw data ($)
Decision scores
A1
0.14
0.30
1811
0.11
16
0.04
4
0.05
17,600,000
0.07
0.57
A2
0.13
0.31
1804
0.11
16
0.04
4
0.05
20,480,000
0.06
0.57
A3
0.15
0.29
1784
0.11
16
0.04
5
0.04
23,450,000
0.06
0.53
A4
0.14
0.29
1911
0.12
15
0.04
2
0.10
22,900,000
0.06
0.61
A5
0.16
0.26
1890
0.12
15
0.04
2
0.10
26,500,000
0.05
0.57
B1
0.14
0.30
2177
0.14
13
0.05
4
0.05
14,600,000
0.09
0.62
B2
0.14
0.31
2167
0.14
13
0.05
4
0.05
17,180,000
0.08
0.61
B3
0.15
0.28
2137
0.13
14
0.04
5
0.04
21,050,000
0.06
0.56
B4
0.15
0.29
2323
0.15
12
0.05
2
0.10
19,000,000
0.07
0.65
B5
0.16
0.26
2291
0.14
13
0.05
3
0.07
25,500,000
0.05
0.56
C1
0.14
0.29
2731
0.17
11
0.05
4
0.05
12,600,000
0.10
0.67
C2
0.14
0.30
2716
0.17
11
0.05
4
0.05
14,980,000
0.09
0.66
C3
0.15
0.27
2669
0.17
11
0.05
5
0.04
17,450,000
0.07
0.61
C4
0.15
0.28
2965
0.19
10
0.06
2
0.10
16,400,000
0.08
0.70
C5
0.17
0.24
2913
0.18
10
0.06
3
0.07
21,000,000
0.06
0.62
D1
0.13
0.33
3080
0.19
10
0.06
4
0.05
11,600,000
0.11
0.74
D2
0.12
0.35
3060
0.19
10
0.06
4
0.05
13,880,000
0.09
0.74
D3
0.13
0.33
3001
0.19
10
0.06
5
0.04
16,250,000
0.08
0.70
D4
0.12
0.34
3380
0.21
9
0.07
2
0.10
15,100,000
0.09
0.81
D5
0.13
0.31
3313
0.21
9
0.07
3
0.07
19,500,000
0.07
0.72
E1
0.13
0.32
4213
0.26
7
0.09
4
0.05
8,600,000
0.15
0.87
E2
0.12
0.34
4176
0.26
7
0.09
4
0.05
10,580,000
0.12
0.86
E3
0.13
0.32
4067
0.25
7
0.09
5
0.04
12,650,000
0.10
0.80
E4
0.13
0.33
4797
0.30
6
0.10
2
0.10
11,200,000
0.12
0.95
E5
0.13
0.31
4662
0.29
6
0.10
3
0.07
15,000,000
0.09
0.85
Table 8. Comparing the two highest scores.
Comparing/match
E4 (777G-6015)
E1 (777G-365C L)
Investment (Million $)
11.2
8.6
Number of trucks
6
7
Number of excavators
2
4
Daily transport capacity (tons)
4797
4212
Unit cost ($/ton)
0.1255
0.1288
Total words in MS: 8668
Total words in Title: 20
Total words in Abstract: 229
Total Keyword count: 6
Total Images in MS: 11
Total Tables in MS: 16
Total Reference count: 71